Capital improvements

Construction updates

Closures and access changes during the work, newest first.

Each entry is a transcription of a notice posted in the lobbies. Where this page and the paper notice differ, the paper notice is correct.

Notices, newest first

  1. Asbestos abatement in the cellar

    Posted · link to this notice

    Building
    2520 Batchelder StreetBuilding 3 on the schedule
    Work dates
    1 to 18 September 2026
    Working hours
    7am to 4pm

    Closures and access changes

    The cellar is not shut for the whole period: one section at a time is sealed off, and signs marking the no-access zones are posted on site.

    Closures in the 2520 Batchelder Street cellar, 1 to 18 September 2026
    Dates Section What that means
    Tue 1 to Thu 3 Sep A · Bicycle room The bicycle room is sealed off.
    Fri 4, Tue 8, Thu 10 to Fri 11 Sep B · East end The east end of the cellar is sealed off. You will not be able to get between 2540 and 2520 Batchelder through the cellar, in either direction.
    Wed 9 Sep, 6pm to 6am D · Through corridor The widest closure. The through corridor is sealed off. Residents of 2520 have no access to the cellar at all, there is no way between the cellar and the parking lot in either direction, and the laundry room is closed.
    Mon 14 to Fri 18 Sep C · West end The west end of the cellar is sealed off.

    What to do

    • Take out anything you need from the bicycle room and the storage rooms before that section is sealed.
    • Do the laundry before the evening of Wednesday 9 September. The laundry room is closed 6pm to 6am that night.
    • On the night of 9 September, walk in from the street. There is no way through the cellar to the parking lot.
    • Follow the no-access signs posted on site. They mark the sealed sections.

    Where this came from

    Issued by
    Solstice Project Services, the owner’s representative for the capital improvement work.
    Contractor
    AM&G and their abatement subcontractor.
    Questions
    The management office, (718) 646-9080. The paper notice in the lobby also names a project manager and gives a direct number.

    Transcribed from the notice dated 31 August 2026. That notice writes the end date as 9/18/25; from its own list of dates it means 18 September 2026. Where this page differs from the paper notice, the paper notice is correct.

    Which section is where

    The notice marks four sections on a plan of the cellar. This is what each one covers.

    Section C
    The west end: Storage Room 3 and the compactor room.
    Section D
    The stretch of corridor beside the laundry room. It is short, but it is the way through: sealing it cuts the cellar in two, which is why the closure on 9 September is the wide one.
    Section A
    The bicycle room.
    Section B
    One angled area covering the whole east end: Storage Room 2, the storage room beyond it, and the floor that carries on down the east side past the compactor, towards 2540 Batchelder.
    Schematic of the 2520 Batchelder Street cellar A strip running west to east. At the west end, Section C covers Storage Room 3 and the compactor room. Along the top, west to east: the office, Storage Room 1 and the meter room. Section D is a short stretch of corridor between the top and bottom rows, beside the laundry room. Along the bottom, west to east: the community room, the laundry room, Section A which is the bicycle room, and the compactor. Section B is a single angled area at the east end: a band across the top holding Storage Room 2 and a further storage room, with the east end carried down the full depth of the cellar, wrapping around the compactor. Office Storage Room 1 Meter room Community room Laundry room Compactor SECTION C Storage Room 3 Compactor room SECTION D · corridor SECTION A Bicycle room SECTION B Storage Room 2 Storage room West end East end, towards 2540
    Schematic of the cellar, not to scale and not a floor plan. It shows which rooms fall in which lettered section. The measured plan is the one attached to the paper notice.

About these updates

What this page is, and what it is not

Notices reach residents on paper, posted in the lobbies and handed out in a packet. They are transcribed here so they can be read on a phone, kept after the paper comes down, and linked to one at a time. Nothing is added and nothing is left out, except a contractor’s direct contact details, which stay on the paper copy.

This page is not a substitute for the notice packet. Dates move, and a notice can be replaced by a newer one or by a sign on the door. Where this page and the paper differ, the paper is correct. If you spot an error here, please tell the management office so it can be put right.

How often
There is no fixed schedule. A notice goes up when a phase of the work is about to affect an entrance, a room, the laundry, the parking lot, or the water and heat. Expect several a year while the work runs, to December 2028.
Older notices
Nothing is taken down once the work is finished. Past notices stay on this page, marked as finished, so there is a record of what happened and when.
The long schedule
The construction schedule lists every item of work for all four buildings from March 2026 to December 2028. Its dates are tentative and given in whole months. These updates give the exact days, for one building at a time, shortly before the work starts.

Anything that needs arranging goes to the office

Access to apartments, storage, parking and anything that has to be sorted out in advance is handled by the management office, not by the contractor.

Call (718) 646-9080 The full schedule